LaserBeam: Driver Development & Shipping Update

 

When will the LaserBeam ship?

During my time at Sienci Labs, I have learned a lot about rapid prototyping, quality control, and listening and working with our amazing community. Andy & Chris our Founders have always advised me to always give myself more time than needed. It’s a lesson I have not fully taken in until now, I feel like I have learned to set more realistic expectations on the timelines it takes to develop a new product. I do believe for the price, we are developing the best laser diode attachment on the market. The last piece of the puzzle is a 5A laser driver that meets the standards of the company and my own. I have no doubt that we will get there but we need time. The driver needs to work well, be tested independently and then ordered in bulk. That’s all that is left with development. We are currently at version 5 of the driver prototyping, we may need 1-2 more before I am confident enough to send off for independent lab testing and bulk ordering. The original ship date I picked was the first week of July, then first week of August then end of August. Instead of telling you we can ship early  October. I need to take Andy & Chris’ advice and give myself and those I’m working with enough time to do this right and to not continuously push the date by small increments. Your support on this new product and journey to developing it really does mean the world to me. Thank you Sienci Labs community!  We do hope to ship earlier than the new listed date but I think it’s best to allow more time than I believe we need. 

*Final shipping update is December 2021 (absolute latest)*

What caused this delay?

  • I hired 2 international electronics designers, I misjudged their experience with laser diodes and constant current drivers. 
  • Neither designer was able to develop something that could perform the tasks we needed v1-v4.
  • The best design we received was v4, it had working safety features and delivered current to the diode, only issue was that is was not constant current and was not a high quality design
  • Slow design work pace: I hired these designers in April 2021 and only had received designs that could be tested in July. This is the root cause of our 3-4 month delay
  • I am now disputing the payments we made to them and working with a new local designer full time and he is working night and day prototyping the new laser driver design. 
  • I am working between the Sienci office and our new designers office in order to keep the project moving forward and continuously test and debug designs at a much faster pace
  • This ultimately stems from my own inexperience hiring electronics engineers and designers. This did teach me a lot

5A Laser Driver Update

  • With all that said, version 5 of the driver was tested last night and had some issues
  • To much inductance/resistance in the traces leading to the voltage regulator 
  • Reverse polarity protection was not included
  • The way feedback was provided to the mosfet was causing issues with the constant current
  •  Version 6 is being worked on as we speak and we’ll be placing a new PCB order tomorrow to fix all the issues listed above. 

Production News

  • We have finalized the LaserBeam Logo 
  • Both aluminum & copper heatsinks have been tested with great results 
  • Focus ring & springs have been tested and packaged with great results 
  • We have a stock of 200 7w Diodes
  • Fans have arrived and will be tested next week
  • New batch of power supplies have arrived and will be tested next week 
  • Extension cables are being prepped for packaging 

Timeline (8-16 weeks): What needs to be done?

  1. Driver Development: currently working on v6 of the prototype (1-2 Weeks)
  2. Testing: send a driver off for testing  (1-2 Weeks)
  3. FDA Compliance: file our test reports with the FDA (1-2 Weeks)
  4. Order Drivers: order the drivers in bulk (4-8 Weeks)
  5. Ship: Package and ship LaserBeam Pre-orders (1-2 Weeks)

What If I can’t wait that long?

Please send us an email or give us a call and we will process your refund. I never want to disappoint community members and customers but at Sienci Labs we value transparency over everything. Some of you run your businesses with the Longmill and you anticipated having a Laser for certain projects/jobs, we understand if you need to make different plans and explore other options. 

For those of you who still want to  wait, first of all thank you. It’s because you guys have supported this project from day one that I get to develop a product that the community will use and hopefully enjoy in the very near future.  

Ordering Additional Safety Glasses & Lenses: 

https://sienci-upgrade3.cospark.io/product/laser-accessories/

Check out the link above if you need to order additional LaserBeam accessories that you didn’t order in your original LaserBeam preorder. You won’t be charged any additional shipping and your order will be combined with your LaserBeam Pre-order! 

Sienci LaserBeam Pre Order:

Place your Sienci LaserBeam Pre order here:  https://sienci-upgrade3.cospark.io/product/laser/

Answering your FAQ: 

Send your Laser Questions Here: https://sienci-upgrade3.cospark.io/contact-us/technical-help/

Check out our LaserBeam FAQ video, I take all your unanswered questions from the LaserBeam livestream and try to give you guys more clarity on the LaserBeam add on. 

Stay up to date by signing up for

Subscribe

* indicates required

If you missed the last update, check it out here: https://sienci-upgrade3.cospark.io/2021/07/26/laserbeam-driver-complications/

Inductive Limit Switches – Production Update

Hey everyone here’s an update on the development of the inductive limit switches for the LongMill! If you haven’t read the last post, you can read it here: https://sienci-upgrade3.cospark.io/2021/07/30/longmill-limit-switches-coming-soon/

I know a lot of people are excited about this kit, and I assure everyone we’re working really hard on this. Over the last couple of weeks, we’ve been working on a couple of different things, including video and written info and content, continual testing, assembly instructions, packaging, and the supply chain for the kit. We are now waiting on our first batch of sensors and a couple of other parts to arrive from our manufacturers, and we will be starting packing and assembling the kits as soon as parts start to trickle in. All of the parts for the kit have been ordered and are expected to arrive in mid-September. We expect to start shipping kits a couple days after we’ve received all of the parts. Kits will be $60CAD or around $48USD each.

Our initial timeline for this project was to have a product released at the end of August. However, we had a minor setback due to some changes in part price and availability from one of the sensor suppliers that we initially ordered and tested samples from, so we have acquired samples from two additional suppliers, one of which we’ve fully tested and have decided to move forward with to use for production.

Some a bit more specifics that we’re working on to provide users include information about using different workspace coordinates, returning to a certain part of your job after a power outage or shutoff, and using jigs, which should add some extra tricks and functionality users can add to their machines.

Making your own

As promised in the last post, here are some instructions on making and assembling your own mounts and sensors if you prefer making your own over buying the kit from us.

Please note that these instructions are still in development, and additional resources and videos will be available for users soon. These instructions should help the general user population if they wish to make their own mounts and sensors.

Choosing sensors

The sensors we recommend using are:

Model: LJ12A3-4-Z/BX

NPN Detection

Detection distance: 2mm-4mm

Normally open

Supply Voltage: 5V* 

Choosing the correct voltage option is very important, as this particular type of sensor is more commonly available in a working voltage of 6-36V, which requires additional wiring to make work with the LongBoard. For using higher voltage sensors, you may need to use either the 12V auxiliary power from the board, 24V from the power supply, or from an external power source. That being said, I highly recommend sourcing the 5V variant of the sensor as this will make installation much more simple.

There are many variations of the LJ12A3-4-Z/BX, as well as other M12 sized barrel sensors that come in different lengths. In my experience, most seem to be more than accurate enough for this application, with a repeatability of 1 thou or better.

Most sensors also come with a set of nuts and washers, which can be used for mounting.

Making the mounts

All mounts can be 3D printed. The models can be found on our public Onshape document for the LongMill. The models can be found under Electronics -> Limit/Homing Switches. Right click on the model to export as an STL or your preferred 3D model file format.

These parts can be printed with most FDM printers. If you’re interested in reading about our 3D printing process, please check out this post. I would recommend using a higher infill for these parts since a more rigid part generally helps mounting.

All of the mounts use a pair of M3 heatset inserts. CNC Kitchen has a couple of videos on using threaded inserts on 3D printing that are awesome which talk about them in general as well as how to install them.

For our application, we found a fairly inexpensive and commonly available insert that works great. A drawing of the insert can be found below.

Here is an exploded view of the inserts.

Assembling the mounts

Here is a view of everything assembled before mounting to the machine.

And here is the exploded view:

Attaching to the machine

The mounts slide onto different areas of the machine as shown in the images below. Use the M3 screws to secure them. You will need to position the sensor to a position that lines up the tip (usually blue or orange) with the gantry you are sensing for. Loosen and adjust the mounts as necessary.

Wiring

Although the sensors for our kit will come with pre-wired JST connectors with a 2.5m wire for running through the drag chain, it’s likely that off-the-shelf options will not. You will likely need to extend the wires to be able to run the wires through the drag chains.

The LongBoard comes with ports to connect limit switches via JST4 connectors or with the detachable screw terminal block. Here is a diagram of wiring the inductive sensor using the screw terminal. Note that the 5V and ground lines are shared between all of the sensors, and each black signal wire is connected to their separate axis.

More info on wiring can be found on our resources for limit switches.

Firmware settings

Once your sensors are installed you may need to update your firmware settings to enable the limit and homing functionality. A full outline of all of the related firmware settings can also be found in our resources.

Conclusion

I hope that this information helps some of our more ambition users who don’t want to wait to get a kit from us set up limit switches on their machine. I also hope that this will give you guys a head start in exploring all of the functionality in adding limit switches to your design. Over the next couple weeks, our team will continue developing the resources for the installation of the switches, so I highly recommend staying in tune on our social media and our blog, and check back on our resources page to check for updated resources!

LongMill limit switches coming soon

Hey everyone. One highly requested add-on for the LongMill has been limit switches. For the uninitiated, limit switches are often used on CNC machines for 1) homing the machine 2) preventing the machine from reaching the limits of its travel. If you’re interested in reading more about what limit switches are and what they can do, I recommend reading the article in the Resources.

Please note that in this post, we are using the term “limit switches” and “homing switches” interchangeably. I do understand that there is a small distinction for both, but for this application, they are basically the same.

At the beginning of LongMill development, limit switches were not a priority as a feature when focusing on beginner hobby CNCers. This primarily came down to a few factors. First was the added complexity of having limit switches, which means additional setup and assembly for the user, as well as adding to the learning curve of learning how to use limit switches. Secondly, with the LongMill set up so that crashing the machine will not damage itself, limit switches are not necessary to protect itself. For customers still adamant about having limit switches, we still provided full hardware support to plugin or wire in switches directly into the controller, which would take care of a small population of more advanced users.

For those who want to read more about community made limit switch solutions, this is a great thread to read: https://forum.sienci.com/t/homing-limit-switches/99/41

We still hold our opinion that beginner users do not need limit switches with their machine to get the full functionality of the machine, and we recommend starting out without them until a better understanding of the machine and its use is achieved. However, as our community has grown and along with that their experience, more and more users are now exploring new ways to bring advanced features to their machines. Not only that, the development of our very own gSender now allows us to integrate software and hardware more closely than ever before. With these things in mind, we’ve spent some time creating our own plug-and-play solution for the LongMill.

Creating a limit switch solution specific to the LongMill came with several challenges.

First was the lack of foresight on providing mounting points for limit switches. This simply came down to the fact that we did not integrate mounting points on the LongMill for adding limit switches. Later versions of the LongMill did come with holes and other features that could mount sensors, however, with so many different versions of the LongMill, it would be difficult to document and provide resources for installing limit switches for every single version of our machine.

Second was the voltage support of the sensors we need to use for the limit switches. We are using a variant of the LJ12A3-4-Z sensor as our limit switches, a very common and widely used sensor. However, almost all variants of this sensor are designed for a 6-36V input voltage. Although it is possible to pull 12V power from the LongBoard, the JST 4 pin connectors already integrated into the board which was designed to be used for a plug and play solution were designed for 5V only. In hindsight, it may have been a better idea to route the 12V power to the JST connectors, but this meant that we would need to purchase 5V compatible sensors, which do exist but are more difficult to source, to be compatible with the LongBoard. Our first supplier for the sensors created the proper wiring and plug set up for the LongBoard, but unfortunately, they were only able to provide 6-36V sensors which meant that we had to start looking for a new supplier.

The new design overcomes these two challenges. First of all, the mounting hardware for the limit switches will allow users to install their sensors to any version of the LongMill, as well as allowing the flexibility to choose which side of their axis they want to mount to. For example, some users may want to home from the bottom left corner of their machine and some may want to home from the upper left corner of their machine. Users only need to move their sensor from the front of the machine and remount it to the back and specify the change in the software to make the change. Second, we have re-sourced and tested a 5V variant of the LJ12A3-4-Z sensor, which will provide proper voltage compatibility with the LongBoard. This supplier will also be providing us with the proper wiring for a plug-and-play installation of the limit switches.

We expect the kit to be ready for sale and shipping around the end of August. Each kit will come with three sensors with a plug and play wiring harness which should have an installation time of around 15-20 minutes. The price for each kit will be around $60CAD or $48USD. Additional resources and software setup support will also be provided with the kit. We’ll also be publicly releasing the designs and specs for the kit for users that want to make their own setups. Please check our blog, email, and social media for further announcements.

Today’s testing of the sensors have shown repeatably of over 1 thou which should offer a very precise way to home the LongMill.

I’m excited to see the limit switch kit in the hands of LongMill users soon and look forward to seeing the rest of the development team and the community come up with ways to utilize homing on the LongMill!

July and August 2021 Production Update

Hi everyone, this is a production update for July and August. I’m happy to announce that we are expecting the lead times for the next 400 machines to be 1 to 2 weeks (update, as of August 10, lead times for LongMills is under 1 week). For the most part, we expect most machines to ship within a few days. Any orders that are still pending shipment at the time of writing should be shipped by Tuesday of next week.

All of the parts that we were waiting on for this part of the batch have now arrived and we should not be seeing any major delays in shipping for roughly the next 8 weeks.

During part of July, we ran into some part shortages, such as with our control boards, Delrin anti-backlash nuts, and drivers. We also had a short period of time where our print farm was also shut down due to a shortage of filament. These shortages were caused primarily due to shipping delays. We’ve finally have gotten all of our parts without much issue, and can continue production.

At this point, we will be able to produce another 400 units without running into supply shortages. There are still a number of components we expect to start running out of once we ship the 400 units, including:

  • Rails
  • Gantries and other steel components
  • Control boards

We have placed orders for these items at the time or writing or are in the process of ordering these parts.

In any case, that’s our update for this month (and August). Happy making!

LaserBeam: Driver Complications

Hey everyone, Ikenna here with another LaserBeam update. I’m excited to see parts continue to arrive, with little to no QA issues. At this moment the majority of my time is focused on the 5A Driver development, our first prototype did not work as intended. Fortunately we have 2 separate designs and will be testing the second design late next week when the PCB arrives. At the same time we are reworking the schematic for the first design so we have more options and will give us the best opportunity to provide the best driver for the 7W LaserBeam. 

We expect to begin shipping Monday August 30th at a pace of about 25-50/week. We should be able to clear the order queue within 4-6 weeks from when we begin shipping. The challenges are completing a working driver, receiving acknowledgement from the FDA of test report submission, and receiving a large order of driver pcbs from our overseas supplier.

Driver Development:

Driver A-v1.1:

  • Unfortunately this design was not able to interpret the 5V PWM signal that comes from the Longboard
  • Mandatory Safety features did not work as designed; Key switch, interlock and power off reset

Driver A-v1.2:

  • We broke down each function that wasn’t working with Driver A-v1.0 and I’m more confident that this new design fix the initial issues we saw
  • DriverA- v1.2 Is being troubleshooted, then pre-tested before a new PCB prototype is made, assembled and tested against all functions that we need for the ideal driver

Driver B-v1.1:

  • Assembly has been completed and shipped
  • We had the manufacturer send the PCB early because we can finish soldering components very quick and that should save us a day or two
  • Will arrive July 29th 2021 and the goal is to  be fully tested by July 31st
  • If we find any functionality issues during testing we will begin to troubleshoot and rework this design

Local Designer:

  • To help speed up the prototyping process, we have begun working with a local electronics designer that already has experience working with Sienci Labs
  • His main objective will be to work with our current designers and help change designs at a quicker pace
  • He will also be able to populate and solder components onto new PCBs for prototyping faster than our overseas manufacturer can. Allowing us to test new designs within 7 days

Driver Design Compliance:

We are working with TÜV SÜD in order to independently test our LaserBeam to make sure we are in compliance with Health Canada, FDA and International Laser Standards. Testing can only begin once a 5A Driver design passes our tests so it acts as our bottleneck. TÜV SÜD testing procedure will ensure all safety functions work correctly, and our user/safety manual has all the information needed for safe operation. Until then we will continue working on our user/safety manual so it is as detailed as possible. We have also been completing the necessary FDA registrations so we can submit our reports in a timely fashion.

Production Heatsinks and Lens Focus Ring:

The manufacturing of the aluminum heatsink, copper heatsink and lens focus ring has been completed. The aluminum heatsink and lens focus ring has been anodized (black) and is being shipped now. This updated design should allow the G2 lens to be easily focused and solve the issue we had with the prototype heatsinks. As soon as they arrive we will begin quality assurance then assembly of the 7w diode, heatsinks and exhaust fan. The diode/heatsink/fan assembly is 50% of the 7W LaserBeam and the 5A driver, enclosure and air assist  is the other 50%.

Power Supplies:

Power Supplies have arrived and passed QA tests, connectors have been attached. We will have to repackage them with the AC cables as the box they came in does not fit both the power supply and the AC cable. 

Safety Glasses:

Safety Glasses have arrived and look great with the Sienci Labs branding.  

Designs:

  • Laser Driver Enclosure: We have a rough design set, small changes once the driver is completed to accommodate all connectors, switches etc. 
  • Air Assist: We have improved the design with a sliding pressure fit and an articulating nozzle instead of a funnel design. But we are reworking new designs until we are satisfied 
  • Packaging: I will start playing with packaging ideas, nothing concrete until more production parts begin to arrive.

Testing:

  • PCB Design A: 5A Driver A-v1.1 failed testing, currently working on 5A Driver A-v1.2 (schematics look promising)
  • PCB Design B:  5A Driver B-v1.1 will arrive Thursday for testing. I had the manufacturer ship with a few parts unsoldered in order to save a few days and test earlier. We are comfortable soldering the remaining parts inhouse
  • Laser Diodes: Testing a new 7w diode supplier this week

Supply Chain:

  • Thermal Paste: Samples will be ordered Monday
  • Extension Cables: Connectors have been ordered, we ordered a small batch of wire to test
  • Lens Focus Rings: Completed and are being shipped
  • Aluminum Heatsinks: Completed and are being shipped 
  • Copper Heatsinks: Completed and are shipped
  • Laser Diodes: Currently have 150pcs 7w Diodes in stock another 50pcs were shipped last week

 Ordering Additional Safety Glasses & Lenses: 

https://sienci-upgrade3.cospark.io/product/laser-accessories/

Check out the link above if you need to order additional LaserBeam accessories that you didn’t order in your original LaserBeam preorder. You won’t be charged any additional shipping and your order will be combined with your LaserBeam Pre-order! 

Sienci LaserBeam Pre Order:

Place your Sienci LaserBeam Pre order here:  https://sienci-upgrade3.cospark.io/product/laser/

Answering your FAQ: 

Send your Laser Questions Here: https://sienci-upgrade3.cospark.io/contact-us/technical-help/

Check out our LaserBeam FAQ video, I take all your unanswered questions from the LaserBeam livestream and try to give you guys more clarity on the LaserBeam add on. 

Stay up to date by signing up for

Subscribe

* indicates required

If you missed the last update, check it out here: https://sienci-upgrade3.cospark.io/2021/06/23/laserbeam-moving-along/

LaserBeam: Moving Along

Hey everyone, Ikenna here with another LaserBeam update. We have made a lot of good progress since the last update. Most significantly we’ve tested our sample production heatsinks with great results, and our prototype LaserBeam drivers will be arriving from the manufacturer in the next week or two. 

5W Generic Banggood Laser Power Test:

When testing the 5W Generic Banggood laser we were able to confirm that the real continuous optical power of 1.9W-2.2W which is far below the promised 5W continuous power rating. These lasers have their place in the market but if you are looking for high quality at a reasonable price I believe the Sienci LaserBeam is the best offering on the market. In the pictures below the top mW reading is the true optical power reading for this specific laser system. (1.95W, 2.13W)

7W LaserBeam Laser Power Test:

When testing our 7W laser diode we were able to confirm real continuous optical power of between 7.1W-7.2W @ 4.5A (recommended current limit for longevity) which will keep both the diode and driver running for a long time as well as producing the exact power we are promising you, which cannot be said about lower quality laser systems like the one in the previous section. In the picture below the top mW reading is the true optical power reading for this specific laser system. (7.17W, 7.18W)

Sample Production Heatsinks and Lens Focus Ring:

Last week we received some sample production heatsinks and lens focus rings. Good news, the heat dissipation is great and was able to keep the laser system 6 degrees celsius cooler than the generic heatsink when running our max power test file. Everything fits well and was assembled with relative ease. The bad news is that the top of the copper heatsink was just 2.5mm too long for the G2 lens to properly focus, using a very thin 3d printed lens focus ring I was able to get the G2 lens in focus. This  confirmed that I needed to reduce the size of the top copper heatsink by 3mm to make everything work, as well as sliding the set screw location down 3mm on the Aluminum heatsink. These changes have been sent to our manufacturer and they have begun production again. 

5A Driver Prototype: 

I have been working very hard with our PCB designers and our PCB manufacturer to find any potential issues and solve them before we receive the prototypes and begin testing and designing our enclosure. Over the next 2 weeks we will be working with experienced testing labs to produce a comprehensive testing procedure for all LaserBeam 5A drivers. We will also use the prototypes to start creating our safety and assembly manuals.

Safety Glasses:

Our safety glasses are ready and being shipped now. I have been using a these exact glasses to run all our LaserBeam testing and can confirm with my own experience as well as laser power testing that these are great safety glasses and your eyes will be well protected. 

Designs:

  • Laser Driver Enclosure: I am waiting to receive and test our prototype LaserBeam Driver, I will continue to iterate designs until I can test them with the physical driver boards. 
  • Magnetic T-mount: The standard T-mount design is finished so I will begin looking into designing a magnetic mount.
  • Magnetic Air Assist: The main design is complete, I am now sourcing neodymium magnets to test
  • Packaging: I will start playing with packaging ideas, nothing concrete until more production parts begin to arrive.

Testing:

  • Power Supply: 12V 7A power supply has been tested successfully, I will continue to test 12V 7A to make sure we get the right power supply for the 5A driver and all the fans. 
  • PCB Design: Waiting to receive the driver prototypes, in the meantime devising a comprehensive testing procedure. 
  • Laser Diodes: I am currently testing a secondary supplier for the 7W Laser diodes to ensure that we have a backup if our initial supplier has a shortage.

Supply Chain:

  • Lenses: Tested production order successfully, in stock.
  • Lens Focus Rings: Tested product samples successfully, currently being manufactured.
  • Aluminum Heatsinks: Made one last small change to the copper heatsink set screw location, currently being manufactured. 
  • Copper Heatsinks: Made one last small change to the top copper heatsink size to make it easier to focus the G2 Lens, currently being manufactured  
  • Safety Glasses: Production is complete, and has shipped. 
  • Laser Diodes: Currently have 100pcs 7w Diodes in stock, currently testing a 6W diode to offer a secondary power option.

 Ordering Additional Safety Glasses & Lenses: 

https://sienci-upgrade3.cospark.io/product/laser-accessories/

Check out the link above if you need to order additional LaserBeam accessories that you didn’t order in your original LaserBeam preorder. You won’t be charged any additional shipping and your order will be combined with your LaserBeam Pre-order! 

Sienci LaserBeam Pre Order:

Place your Sienci LaserBeam Pre order here:  https://sienci-upgrade3.cospark.io/product/laser/

Answering your FAQ: 

Check out our LaserBeam FAQ video, I take all your unanswered questions from the LaserBeam livestream and try to give you guys more clarity on the LaserBeam add on. 

Stay up to date by signing up for

Subscribe

* indicates required

If you missed the last update, check it out here: https://sienci-upgrade3.cospark.io/2021/04/12/laser-development-update/

LaserBeam: What’s Next?

Hey everyone, Ikenna here with another LaserBeam update. Pre-order went live a few weeks ago and we are very happy with the customer response, we now have a pre-order page for any LaserBeam accessories you might want. Lots of testing, ordering and designing is still underway but we are making progress very quickly.

Preorder your LaserBeam!

https://sienci-upgrade3.cospark.io/product/laser/

Ordering Additional Safety Glasses & Lenses: 

Check out the link below if you need to order additional LaserBeam accessories that you didn’t order in your original LaserBeam preorder. You won’t be charged any additional shipping and your order will be combined with your LaserBeam Pre-order!

https://sienci-upgrade3.cospark.io/product/laser-accessories/

Answering your FAQ: 

Check out our LaserBeam FAQ video, I take all your unanswered questions from the LaserBeam livestream and try to give you guys more clarity on the LaserBeam add on. 

Designs:

  • Laser Driver Enclosure: I am waiting to receive and test our prototype LaserBeam Driver, I will continue to iterate designs until I can test them with the physical driver boards. 
  • Magnetic T-mount: The standard T-mount design is finished so I will begin looking into designing a magnetic mount.
  • Magnetic Air Assist: The main design is complete but finding a way to mount the magnets and optimize the design to print better.
  • Packaging: I will start playing with packaging ideas, nothing concrete until more production parts begin to arrive. 

Testing:

  • Power Supply: I am currently testing the LaserBeam driver power supply. 
  • PCB Design: Waiting to receive the Driver prototypes, in the meantime devising a comprehensive testing procedure. 
  • Laser Diodes: I am currently testing a secondary supplier for the 7W Laser diode to ensure that we have a backup if our initial supplier has a shortage.

Supply Chain:

  • Lenses: Currently being manufactured.
  • Lens Focus Rings: Currently being manufactured.
  • Aluminum Heatsinks: Currently being manufactured. 
  • Copper Heatsinks: Currently being manufactured.
  • Safety Glasses: Currently being manufactured. 
  • Laser Diodes: we currently have 50pcs in stock. Looking to order more as soon as possible.

Lens Descriptions

Lens TypeDescription 
G2 Lens has the best efficiency (most power) and shortest focal length so it’s great for cutting and good for engraving 
3 Element Lens 3 Element has the cleanest beam profile (super detailed text, lines and image engraving)
G7 Lens has a good balance between the power of the G2 and the clean beam profile of the 3 Element.
G8 Lensis very similar to the G7 but it has a smaller focus length so you can engrave thicker material than the G8 because you would have more available Z axis travel. I will make a dedicated video for lenses but hopefully that gives you a bit of clarity until then.

Lens Test File

G2 Lens
3 Element Lens:
G7 Lens:
G8 Lens: 

Material Guide Chart

Youtube Video Guide: https://youtu.be/EizUVtjLsRw

MaterialCuttingEngraving
3mm PlywoodLens: G2
Speed: 2.2 mm/s
Power: 100%
Passes: 3
Z step per pass: 1mm 
For cleaner finish decrease power and z step per pass, increase speed and number of passes
Lens: G2
Speed :25.4 mm/s
Power:100%
Passes: 1

Decrease speed for deeper and darker engraving 
6mm PlywoodLens: G2
Speed: 2.2 mm/s
Power: 100%
Passes: 5
Z step per pass: 1.2mm
For cleaner finish decrease power and z step per pass, increase speed and number of passes
Lens: G2
Speed :25.4 mm/s
Power:100%
Passes: 1

Decrease speed for deeper and darker engraving 
1/4″ PlywoodLens: G2
Speed: 5 mm/s
Power: 100%
Passes: 16
Z step per pass: 0.4mm
Lens: G2
Speed :25.4 mm/s
Power:75%
Passes: 1
1/8th Acrylic (Opaque) Lens: G2
Speed: 2.2 mm/s
Power: 100%
Passes: 3
Z step per pass: 1mm
Lens: G2
Speed :25.4 mm/s
Power:100%
Passes: 1
Organic Leather
Organic Leather tends to shrink and deform when cutting is attempted. Although one may be able to cut organic leather. Beware that as the leather shrinks and deforms it can become a fire hazard as the laser is no longer focused. 
Lens: G2
Speed :25.4 mm/s
Power:75%
Passes: 1
3mm Corrugated cardboardLens: G2
Speed: 5 mm/s
Power: 75%
Passes: 2
Z step per pass: 1.5mm
Lens: G2
Speed :25.4 mm/s
Power:75%
Passes: 1

Stay up to date by signing up for

Subscribe

* indicates required

If you missed the last update, check it out here: https://sienci-upgrade3.cospark.io/2021/04/12/laser-development-update/

June Production Updates

Hey everyone, this is our June production update. For previous production updates and other company news, please check our blog.

It’s continued to be a busy month for April, but as we talked a little bit in our previous update for April/May, we have continued to shorten our lead times. We’ve taken the time to train some of our staff on new responsibilities and reorganize and plan production for the coming months. We are near the end of our run of Batch 4 machines and are starting to prepare for shipping Batch 5 in June.

In terms of COVID, Ontario has slowly seen a decrease in cases and more of our staff are becoming vaccinated. We are fortunate to have had no cases so far, and hopefully none until the end of the pandemic.

A new batch of motors, lead screws, and drag chains

Lead Times

Lead times are expected to average around 1-2 weeks for this month, however we are starting to face shortages in parts that will rely on the timely arrival to keep up with production. Some of these parts include:

  • E-stops
  • Touch plates
  • Arduinos
  • Delrin V-wheels

We expect these parts to arrive in 1-2 weeks. However, this may change if we face delays in transit. We will keep lead times updated on the product page to account for these changes.

Supply Chain

There have been some minor bumps along the way in terms of supply chain especially due to current worldwide events, but luckily with early planning and dedication from the manufacturers we work with, the supply chain process for Batch 5 has been relatively smooth.

One area that we’ve seen a large spike in prices have been with drivers and Arduinos. Due to the chip shortage, many of the components that go into the LongBoard controller have gone up in price. Most ICs that go into this production have doubled in price, and new products that we are working on that involve chips may be delayed due to the unavailability of chips. We have acquired parts for the next 500 controllers with approximately another 100 controllers in stock, but we may need to be cautious of continuing shortages for the rest of 2021.

On the topic of spiking prices, steel prices have gone up more than double since the start of the pandemic, affecting the price of gantries and other steel components that go into making the LongMill. On a lesser level, copper, tungsten carbide, and other raw materials have increased overall prices for many components as well such as E-stops and end mills. Cardboard shortages with our packaging manufacturer have also affected costs and lead times a few times over the last few months too.

Luckily due to improving processes and increasing batch sizes, we have been able to find other ways to save costs and so we don’t expect to have major changes in pricing for our products, however, it is a reality that we may need to face at some point that our company will have to account for changing material prices by increasing the prices of our products.

We have also been affected by the shipping fiascos that have been happening around the world as well. Although we weren’t directly involved in the Suez Canal crisis, we have experienced slowdown in some shipments due to this situation. At the time of writing, most of the parts that we need for Batch 5 production are in transit within Canada (by rail) or are in production with local manufacturers. A couple of parts that we are still waiting on that are in transit by sea include:

  • Router mounts
  • Couplers
  • Delrin nuts
  • 3D printer filament

The remaining components for Batch 5 are expected to arrive this month but won’t be complete for shipping until these parts arrive.

Manufacturing

There have been a few changes in manufacturing at Sienci Labs. Here are some of the things that have been going on.

One small change is the material that we have made the ACME nuts from, switching from stainless steel to brass. Brass has shown to be easier to work with in terms of manufacturing and forming threads. In previous manufacturing batches, a portion of nuts were rejected due to rough threading that made it difficult to thread onto the lead screws. The new brass nuts are of much better quality.

As part of the transition from steel shoulder brackets and drag chain mounts, Batch 5 kits will use M8-16mm bolts instead of M8-25mm bolts to mount these parts. There is no functional change, as the longer bolts are a carryover from when longer bolts were needed on the 3D printed parts.

Next, we are switching to e-coating our gantries from powder coating. We believe that e-coating is an excellent alternative to powder coating as it provides a cleaner, more consistent surface which is important for our XZ gantry assemblies. In some of our recent batches of powder-coated steel, we were running into issues where paint contamination and dripping would either produce cosmetic defects or affect the assembly of the parts because of the unevenness of the surface. E-coating does have a thinner surface, which theoretically means that it offers less scratch resistance on parts. However, based on samples that we have been provided of our parts after being e-coated, we have seen significantly better resistance to chipping and surface quality, without much difference in scratch resistance. This change should decrease manufacturing costs while improving overall quality.

In the last batch, we switched to using M3 screws with captive washers to help keep the screws from coming loose. For these screws, we have switched from stainless steel screws to Class 12.9 alloy, which is a much stronger screw that will prevent head stripping. Head stripping has been a minor inconvenience as removing stripped screws takes a while.

We’ve added three new CR30s (3D Print Mills), a belt based 3D printer. These machines will add additional 3D printing capacity with the benefit of being able to continually print repeated parts. We are currently in the stage of testing and tuning these machines, but we expect each printer to do the work of 4 standard 3D printers, increasing our print capacity by approximately 25%.

Design

Batch 5 comes with some very minor design changes to the LongMill.

First to mention is that motor shafts on the X and Y will be fully round. This is due to a very small number of customers reporting their motor shafts breaking off. The engineers at LDO Motors and us have confirmed that the full shafts will prevent this.

We are manufacturing a slightly modified 65mm router mount to eliminate the need to use M5-12mm screws. Because of the drill tap depth of the four mounting screws in the back of the router, shorter M5 screws were needed compared to the rest of the machine assembly. With the new router mounts, M5-25mm screws can be used on all parts of the router mount. We have also relocated the additional tapped holes that are used for mounting to the front of the mount for easier installation of accessories such as the LaserBeam.

New ACME Delrin nuts have been manufactured without the counterbore, which were an unnecessary feature for our application.

Shipping

Shipping to US and Canada have been reliable overall and seems to have returned to pre-COVID speeds.

We had some delays with Canada Post shipments going to the US via US Air Parcel, so as an alternative we would recommend using UPS.

We have had several issues with customs for shipments going to Mexico this past month that are new. If you have an order that needs to go to Mexico, please let us know in case we need to make other arrangements.

What is a G-Code Sender or CNC Machine Interface?

Hey everyone. We get a lot of questions about software for CNC machines, part of which includes using a g-code sender or machine interface. If you’ve ever gotten technical support from us, there’s a good chance you might have talked to Kelly, who took some time to make this video to help answer the common questions and discuss common functionality in the software.

This video covers some of the basic features that are in g-code senders like UGS and our very own gSender.

gSender Surfacing Tool now available

gSender downloads are now public. Find downloads here: https://sienci-upgrade3.cospark.io/gsender/

Our development team have been working hard to continue making gSender better. Our latest update improves overall performance and reliability, as well as working on new features. The latest version now comes with a surfacing tool that makes it easy to surface your wasteboard using the built in tool.

This tool lets you import your basic settings such as your tool size and speed to automatically generate the toolpaths to run on your machine. Not only can you use this to surface your machine, but you can also use it to surface other stock by changing the size on the tool.

If you aren’t on the latest version of gSender, your gSender program will have a green arrow to indicate an update is available on the upper left side where the gSender logo is.

Additional gSender Documentation continues to be in development. Feel free to check it out to learn more. Continue to stay tuned as more changes and updates come to gSender!